Greetwell crossroads set for major upgrade
Comments Off on Greetwell crossroads set for major upgradeDrivers travelling between Kirton in Lindsey and Scunthorpe will benefit from improvements to a busy junction, with new traffic lights and resurfacing planned to make journeys safer and smoother.
The junction connecting the B1398, Messingham Road and Brigg Road at Greetwell is set for a major upgrade, with work scheduled for early next year.
The improvements will include new traffic signals, a refreshed road surface and clearer road markings, helping drivers navigate the junction more safely and keeping traffic moving.
Cllr Rob Waltham, leader, North Lincolnshire Council, said: “We are continuing to invest in the roads people use every day, making important junctions safer, more reliable and fit for the future.
“This is a busy route linking communities with Scunthorpe and is used by residents, buses and businesses every day.
“This investment will see the junction comprehensively upgraded, including new traffic signals and resurfacing, helping keep people moving safely.”
The latest scheme forms part of a major highways improvement programme, with work taking place in more than 40 towns and villages across North Lincolnshire.
Work has already been completed at 140 sites identified for improvements, including resurfacing, surface dressing, traffic signals and other highway upgrades, with further schemes scheduled in the months ahead.
The B1398 is an important connection between Kirton in Lindsey and Scunthorpe and is regularly used by buses, HGVs and local traffic.
improvements are also moving forward at Scawby crossroads, as part of the council’s wider investment in the route.
The original scheme was revised following feedback from residents, ensuring the planned improvements better reflect local concerns and how the junction is used.
Progress has also been affected by complex underground utilities, technical challenges and land ownership. These have now been resolved, clearing the way for the scheme to move forward.
Cllr Neil Poole, deputy leader of North Lincolnshire Council, said: “We’ve delivered a huge programme of road improvements across North Lincolnshire this year, and that work is continuing.
“Our teams will be out throughout the winter, maintaining roads and tackling problems as they arise, but we’re also looking ahead.
“We’re already putting plans in place for the next wave of improvements in the spring, so we can build on the progress we’ve made and keep investing in the roads residents rely on every day.”
The new signals are scheduled to be installed during the first week of March 2027.
Temporary traffic lights and traffic management will be required while the work takes place, with some temporary footway closures and diversions.
Further details about the programme and any traffic restrictions will be confirmed.